Projects

Marine Corps Logistics Base 

Date: 2012
Location: Barstow, California
The Problem: The US Marine Corps Laboratory Base has a ground water remediation plant with10’ diameter Granulated Activated Carbon (GAC) vessels.  They needed a company with prior experience to inspect the vessels and determine all necessary repairs.  The GAC vessels were originally lined with vinyl ester l, a difficult lining to apply that requires experience to be done correctly.   There are visible rust stains from the exterior and a hole in the steel with water leaking out. At this point we assume a thorough analysis and a substantial amount of work will be needed to get these vessels in good working condition. Complete Job Safety Analyses (JSAs) and site-specific safety plans are required prior to starting any work.

The Solution: Goodwest submits complete and thorough safety plans to a board of specialists and demonstrates their ability to perform the work in a safe manner. Goodwest has extensive experience in water treatment systems in partnering with companies like Siemens Water Technologies, which was the company contracted to remove the carbon from the vessel prior to Goodwest’s inspection.

CLICK HERE for more information about Goodwest’s experience with Walter Filtration systems

At work repairing GAC vessels, chlorobutyl rubber, clear polyurethane
At work repairing GAC vessels

Cal State University Long Beach

Date: 2010
Location: Long Beach, California
The Problem: The concrete was so degraded, spalled, and full of “bug holes” that most lining materials could not be used to successfully reline the half-million gallon subterranean concrete pit. The concrete normally would have required costly and time-consuming re-surfacing prior to relining. Every summer the University filled the pit with more than 100,000 cubic feet of ice and blew air through it to chill their A.C. air and drastically reduce their electricity bill.

The Solution: With summer fast approaching, Goodwest was contacted to utilize the ECOSYSTEM® expansion technology for this project. This system involves injecting an inert gas into elastomeric polyurethane to “expand” the polyurethane film and create a light-weight, very thick lining material that can easily form a pinhole-free surface over extremely uneven surfaces.  Just before the summer heat picked up, Goodwest successfully relined the pit and the University didn’t have to pay more of those exorbitant summer electricity rates.
ECOSYSTEM expansion technology is one of a wide variety of corrosion protection solutions that Goodwest provides for facilities throughout the west.  Goodwest inspects and analyzes challenging corrosion problems, engineers unique long term solutions, and provides turnkey installation services.  Large operations across the full spectrum of industries have utilized Goodwest for decades to ensure their equipment stays in service for as long as possible without problems.

CLICK HERE for more information about Goodwest’s experience with Facilities Maintenance Projects: 


 

Dow Chemical

Date: 2010
Location: Northern California
Scope: 35' diameter x 32' high hydrochloric acid storage tank. Abrasive blast, install, and steam cure Polycorp 1000 triple-layer natural rubber lining.

Acid Tank Relining Natural Rubber Lining of Acid Tank

Lockheed

Date: 2009 & 2010
Location: Southern California
Scope: Dozens of groundwater filtration vessels. Inspect, engineer repair procedure, remove tank piping & components, repair linings, re-install internal & external piping & components. Repairs included abrasive blasting and relining of tank compartments with Enviroline 230 100 % solids NSF 61 potable water epoxy.

Potable water epoxy lining Tank compartment abrasive blasting Lockheed protective linings

U.S. Navy

Date: 2010
Location: Goodwest shop
Scope: 11' dia. x 40' long fuel storage tank. Abrasive blast & line interior w/ Sherwin Williams specialized epoxy & fluorinated polyurethane lining system. Blast & coat exterior with three coat zinc, epoxy, polyurethane.

Fuel Liner with 3 step protective liner

Siemens

Date: 2010
Location: Goodwest shop
Scope: 8 ea. 54" diameter multi-media filter vessels. Inspect, engineer repair plan, piping & component removal, weld repairs, abrasive blasting & relining w/ Endura-flex 1988 elastomeric polyurethane, re-coating of exterior, install internal filtration components, fabricate & assemble CPVC piping, assemble valves, gauges, & control panels.

Filter vessel repair with elastromeric polyurethane

L.A. Metropolitan Water District

Date: 2010
Location: Goodwest Shop
Scope: Water pipeline air release mechanisms consisting of straight pipe, fittings, and flanges. Abrasive blast & coat w/ Amercoat 68HS.

Big Tujunga Dam

Date: 2009 & 2010
Location: Goodwest Shop
Scope: 24", 48", 60", 72" dia. pipe fittings. Abrasive blast, line interior, coat exterior of pipe with 3M Scotchkote 134 fusion bonded epoxy.

Big Tujunga Dam 3M SkotchKote material

Oxnard Power Plant

Date: 2010
Location: Goodwest shop
Scope: 24' w x 12' h x 100' long high-temp. ducting for power plant exhaust. Abrasive blast & apply Amercoat 351 100% solids epoxy containing 880 glass flake additive to interior. Apply Amerguard 400 AL to exterior.

Chemical Transportation

Date: 2009 & 2010
Location: Goodwest shop
Scope: Reline fleet of tanker trailers for bleach transportation with Blair CC-4624 pure chloro butyl rubber linings. For another customer reline fleet of tanker trailers for oil-field frac service with Tnemec 390 100% solids epoxy novolac.

Chemical Tanker butyl Rubber Lining

Download datasheet

Central Basin Water District

Date: 2010
Location: Goodwest shop
Scope: 4", 6", 12" dia. fittings and straight pipe. Variety of exterior coatings (epoxy novolac, fusion bonded epoxy, zinc/epoxy/urethane, polyamide epoxy)

Glendale Water Treatment Plant

Date: 2009
Location: Glendale, CA
Scope: 20' dia. x 21' tall backwash water tank at groundwater treatment plant. Abrasive blast out existing lining and re-line with Carboline Polibrid 705 elastomeric polyurethane. Recoat exterior w/ Carbomastic 15 epoxy & Carboline 134VOC polyurethane.

Steel Mill

Date: 2009
Location: Western U.S. & Goodwest shop
Scope: Pickle line structural supports. Ultra-high hydro-pressure clean corroded steel & residue, abrasive blast & coat I-beam supports in field and in shop with Enviroline 290 100% solids epoxy phenolic. Work around the clock to meet tight schedule.

Olin Chlor Alkali

Date: 2010
Location: Western U.S.
Scope: 30' dia. x 18' high hydrochloric acid storage tank. Remove existing rubber lining using ultra-high hydro-pressure. Abrasive blast, install, and steam cure Polycorp 1000 triple-layer natural rubber lining.

Rialto Airport

Date: 2010
Location: Rialto, CA
Scope: 20' x 40' concrete secondary containment pit for sulfuric acid storage. Abrasive blast, resurface w/ epoxy Carboguard 510 resurfacing compound, coat w/ Carboline Semstone 110 sealer, Semstone 145AFC aggregate-filled novolac epoxy, and an elastomeric Semstone 805 fabric-embedded epoxy in the joint areas.

Elastromeric semstone lining containment

Venezuela Power Plant

Date: 2010
Location: Goodwest shop
Scope: 4', 6', 7' dia. water filtration pressure vessels. Install semi-hard natural rubber linings and epoxy/polyurethane exterior coatings.

Contact us for your protective coating needs. We will ensure your critical equipment lasts as long as possible.

Home | Contact | Privacy Policy | Site Map

© 2013 Goodwest Linings & Coatings
Address: 8814 Industrial Lane / Rancho Cucamonga, California 91730
Phone: 888-499-0085 / 909-987-1774

Rubber Lined Pipe | Tank Corrosion | Abrasive Blasting Services | Elastomeric Polyurethane Coating | Fusion Bonded Epoxy Coating | Pipe Coatings | Polyurethane Linings | Rubber Lined Tanks | Rubber Lining | Secondary Containment Coatings | Water Tank Lining